VT Probes Installation for Monitoring Battery Temperature Only (Refer to Figure 9)
Step
Action
1.
Insert the RJ-45 end of a B-style cable into the J2 Connector on the controller.
2.
If present, cut the brown voltage sense wire on the B-style cable at the 3-pin connector.
Insert the 3-pin connector end into the
3.
receptacle on the 1st VT-Probe.
Place the first probe to the battery post
(as shown in the picture).
Note: Probes are typically installed one
per string, located in the center of the
string.
Note: Do not mount the VT-Probe under
a lug or battery strap. The probe
mounts on top of the lug or battery
strap.
4.
Note: Probes can be mounted prior to
making the connections at the control-
ler. The controller will automatically
recognize the VT-probe.
5.
Verify the number of probes (1) registered with the controller with command:
Connect C-style cables to the 2-position receptacle of the first probe and to the 3-position receptacle of
6.
another probe. cut the brown voltage sense wire at the 3-pin connector
7.
Verify the number of probes (2) registered with the controller with command:
8.
Repeat Steps 6-7 for each probe until all probes are installed.
9.
When all probes are installed, verify they are connected and operating with command:
The controller is now able to make thermal measurements in performing Slope Thermal
Compensation (STC) and battery high temperature disconnect. To enable or verify that STC is active
go to MENU > CONFIGURATION > BATTERIES > BATTERY TEMP MANAGEMNT and select
TEMPERATURE COMP and verify that the feature Temperature Comp is Enabled. If not, configure and
save it appropriately. Additional parameters associated with slope thermal compensation may be set
on the controller to customize this feature.