7. Connect the power cables of the bottom battery from S tep 4 to the side terminals of the top battery. Make
sure that red connects to red and black connects to black.
8. Close the battery covers and connect the PV -MC4 connectors to the system (connection on both sides).
Also, connect all AC cables, the meter communications cable METER, and the Ethernet cable LAN. Then
close the cable box cover. The installation is now complete.
9. Close the lid and tighten the screw.