Section 2: Installation and Start-Up

There are 9 steps to installing and starting-up a 3D TRASAR system.
Unpack and identify
Details
Section
2.1
Unpack all parts and identify them.
Plumb controller
Details
Section
2.4
Plumb utilizing ball valves provided. Inlet
water from recirculating system must be at
5 GPM or greater.
Wiring
Details
Section
2.7
Connect cable between controller box and pellet feeder.
Wire pumps using supplied pigtails (or hardwire). Connect
85 to 250 VAC @ 20 amps power using supplied power
cord (or hardwiring).
Technical Help
(630) 305-CHEM
3D TRASAR
Details
Section
2.2
Install Main Control Panel in well-lit, dry
location convenient to points of use. Mount
at eye level.
Plumb bio-reporter feeder
Details
Outlet
½"
Section
Union
0.5
2.5
GPM
Connect discharge back to recirculating
system downstream from supply in basin
where possible.
Calibration & checkout
Details
Section
2.8
Calibrate probes following instruction on
screen.
521-OM0108.88
Copyright © 2009 Nalco Company
®
5500 - Installation & Operation Manual
Mount controller
Details
Section
2.3
Details
Section
2.6
Details
Section
Install Bio-Reporter feeder
Install Bio-Reporter Feeder in well-lit, dry
location convenient to points of use.
Install probes
ORP Probe
Install probes and attach connectors.
Start-up system
2.9
Enter set points.