Procedure
Step 1 If a battery is connected, turn on the battery switch.
Step 2 Turn on the AC switch between the SUN2000 and the power grid.
Step 3 Turn on the DC switch (if any) between the PV strings and the SUN2000.
Step 4 Turn on the DC switch at the bottom of the SUN2000.
Step 5 Observe the LED indicators to check the operating status of the SUN2000.
● Delivering an upgrade command to the SUN2000 may cause power grid
● Only professionals are allowed to set the grid parameters, protection
----End
Issue 05 (2023-02-17)
NO TICE
connection failure, which affects the energy yield.
parameters, feature parameters, and power adjustment parameters of the
SUN2000s. If the power grid parameters, protection parameters, and feature
parameters are incorrectly set, the SUN2000s may not connect to the power
grid. If the power adjustment parameters are incorrectly set, the SUN2000s
may not connect to the power grid as required. In these cases, the energy yield
will be affected.