Procedure
Step 1 Route the CT cable terminals into the maintenance compartment through the
cable hole at the bottom of the SUN2000, connect the CT terminals based on the
cable labels.
Step 2 Locate the SUN2000 CT terminal in the fitting bag.
Step 3 Connect the prepared cord end terminals to the corresponding ports of the CT
terminal, and insert the communications terminal into the CT terminal base of the
SUN2000.
Figure 5-29 Connect the CT and CT cables
Issue 05 (2023-02-17)
Label
Definition
CT2+
Primary
CT2+
CT2-
Primary
CT2–
CT3+
Reserved
CT3-
CT4+
CT4-