7 – Field Replacement of Load Circuit Breakers
PPENDIX
Instructions for field installation of load circuit breaker. To be performed by qualified electrical 
personnel only. 
1. Remove the A.C. input and turn both battery breakers off. (If the unit is still powered on a
live bus will be exposed creating a possible shock hazard).
2. Remove the top of the unit (there will be 1 screw in each corner and two screws located in
the front center of the unit).
3. Remove the bottom circuit breaker toggle guard.
4. The output terminal block wires are labeled according to their position, locate the wire
corresponding to the breaker position you are installing and connect it to the bottom contact
of the circuit breaker.
5. Attach any hot wire from the bus to the top contact of the circuit breaker.
6. Insert a screw into the hole exposed by removing the bottom toggle guard and screw the
breaker in place.
7. Re‐install the toggle guard and top of the unit and reapply power.
Note: It is normal to measure output voltage on a Centurion II load circuit breaker when its
toggle handle is in the OFF position. The Centurion II circuit breaker alarm circuit produces a
very low current, high impedance signal that can be detected using a high impedance digital
multi‐meter (DMM). This is normal and does not present a hazard to the user.
Newmar • PO Box 1306, Newport Beach, CA 92663
• Phone: 714-751-0488 • E-mail: techservice@newmarpower.com
26

Advertisement

Table of Contents
loading

This manual is also suitable for:

C2rs

Table of Contents