Load Start-up
1. Ensure downstream load connections have been made and there are no loose/floating load
cables.
2. Turn on load circuit breaker, ensuring that the downstream equipment is being powered up
as expected.
3. Ensure the system float voltage on the SM36 is at the level previously noted.
4. Ensure the load current is at a level expected (could be zero if loads downstream have not
been connected).
Prior to leaving the system after it has been commissioned, ensure all AC, DC and
Note:
battery circuits are off. If it is required that the system is to be left on (to power load
equipment, ensure rectifiers are left in their powered up state, and batteries are in circuit.
This will prevent anyone leaving the batteries only powering the load (in which case the
batteries would go flat).