1. Commissioning Process flow chart

Start
System water circuit fully filled
and flushed.
Yes
Carry out air bleed on the
primary circuit
Yes
Carry out air bleed on the
secondary circuit
Yes
System comprise of a single or
multiple units
Multiple
Multiple, detail page 21
Set analogue input method Page
30
Set Hot water outlet control
method Page 32
Set Hot water Temperature
Page 33
Secondary pump control Page
36
Anti Freeze control Page 39
Set local centralised controls
page 51 Note PAR-W31 must be
fitted
No
Please complete
No
Details page 9
No
Details page 11
Single
Single, detail page 19
Sensor method 3 or 6 setup page
25
6
6 sensor method details page 27
3
3 sensor method details page 27
3
Completed
Completed
No