COMMISSIONING

Commissioning
Before normal operation of the
W-001-A
shower, it is essential the following
commissioning procedure is completed
The first operation of the shower is intended to
flush out any remaining system debris, to make
sure that water is purged through the unit and
that the heater unit contains water before the
elements are switched on.
Refit the trimplate by carefully guiding into the
locating slots in the backplate.
Temporarily fit the cover in order to carry out
the commissioning procedure.
a. Offer the cover to the unit. DO NOT connect
the 14-way ribbon cable at this stage.
b. Make sure the valve spindle has the 'flat'
and keyway slot uppermost (12 o'clock
position) as shown in fig.18.
c. Make sure the temperature control lever
is positioned correctly — the lever 'flat'
inside the cover should be uppermost
(fig.19).
d. Carefully locate the cover tags into the
guide pockets on the backplate and make
sure the wires are not trapped.
e. Guide into position so that the control
spindle locates correctly (the 'flats' will only
allow the spindle and lever to fit one way).
Should any difficulty arise, recheck the points
above.
While applying slight pressure to the front cover,
secure in position with the three retaining screws.
Fit the flexible hose (but without the
showerhead) to the shower outlet making sure
the outlet of the hose is directed to waste. Check
the supplied sealing washer is in place.
Turn on the water supply to the shower at the
isolating stopvalve. Switch on the electricity
supply to the shower at the isolating switch.
Water will start to flow through the unit and
discharge from the flexible hose.