Installation Cross-Check - Energizer HOMEPOWER HP-6S Installation Manual

Table of Contents

Advertisement

Sealing the System
Once addressing has been completed, seal the remaining side openings by installing the side cover on the
opposite side of the antenna module on the last unit in the series. E.g. if the system consists of only a Main Unit
with the antenna module installed on the right side, then it should be installed on the left side as shown below.
Fig. 35. Sealing the System
Replacing the IAP's
Before switching on the system, the IAP (Installer Access Panels) need to be replaced.
Main Unit (HP-6M)
1. Connect the ON/OFF cable - orientate the two ends correctly before pushing them together
2. Connect the ribbon cable - ensure correct alignment, the press the connector in firmly so the jaws
close over.
Fig. 36. Replacing the IAP's
3. Carefully arrange the cables to ensure that they are not jammed as you place the IAP back in position.
4. Screw the 4x M4 socket head screws back into place.
Sub Unit(s) (HP-6S) - if applicable
1. Connect the ON/OFF cable - orientate the two ends correctly before pushing them together
2. Carefully arrange the cables to ensure that they are not jammed as you place the IAP back in position.
3. Screw the 4x M4 socket head screws back into place.
V23-00220
6
Energizer Homepower HP-
Series - Installation Manual
34
© Energizer 2022
6
Energizer Homepower HP-
Series - Installation Manual

6. Installation Cross-Check

Before energizing the system, please ensure that the entire Energizer Homepower HP-6 Series system has been
installed following correct procedure. The installer is advised to take sufficient photos of the battery, electrical
wiring and associated switchboards & must complete the start-up procedure described below;
1. Check if the Energizer Homepower (HP-6M/HP-6S) is firmly installed on the wall-mount bracket.
2. Ensure that the electrical conduits & cable entry points are secure & properly sealed.
3. Verify all electrical wiring including the AC, DC, CT sensors & communication cables are correct and
neatly arrange the wires within the Connection Zone.
4. Verify that the addressing switches for all units (HP-6M & HP-6S) are positioned accurately as per
Table 4.
WARNING! The system detects the address of the HP-6M & each HP-6S module only during
start-up, and not during operation. Please ensure that correct addresses are configured prior to
turning the system on via the ON/OFF switch. If incorrect addresses have been set, please turn
off the system via the ON/OFF switch change the DIP switch positions, and then turn the system
back on via the ON/OFF switch.
5. Switch on the Main Unit and the Sub Unit(s), if applicable, by pressing the ON/OFF switch(es) located
on the IAP(s) for 2 seconds. You should notice a short flash on the edge lighting.
6. Switch on Battery Isolator on the Main Unit (HP-6M) then on all Sub Units (HP-6S) if applicable.
7. Turn on the Main Circuit breaker (Grid side) and proceed to turn on any AC Isolators if applicable.
If Backup circuits are connected, then turn on the AC breakers on the Backup side, along with any AC
Isolators and/or connected RCD/RCBOs if applicable.
Residual Current Device & Fault Protection
If the standard local norm or regulation mandates the use of an external RCD (residual current device) or RCBO
(residual current circuit breakers with overcurrent protection) for protection against electrocution or fire risk
by an earth fault, it is recommended to use a Type B RCD/RCBO upstream of the Energizer Homepower HP-6
system. For example, in Australia it is recommended to use a 30mA / 32A, TYPE B RCD to be connected to the
backup circuit, and follow the local electrical requirements for AC supply, e.g. AS 3000:2018.
V23-00220
35
© Energizer 2022

Advertisement