Mechanical Installation; General; Shelf Mounting - ABB 827E Product Manual

Modular inverter system −48 v / +24 v input 120 vac / 240 vac output
Table of Contents

Advertisement

Mechanical Installation

General

This section details all of the information that is necessary to mechanically install the system.
Complete mechanical installation before any electrical connections are made to the system. The
inverter system may be rack or pedestal mounted.

Shelf Mounting

Refer To Figure 5.
NOTE: The DC power plant supplying input circuits to the inverter system must be wired as stated in
Telcordia document GR-1089-CORE, section 9.8.3, Isolated DC return technique. The power
plant must have a dedicated grounding conductor from the power plant common DC return
bus to the Central Office Ground Bar.
This dedicated grounding conductor must not be bonded to or used as the frame ground
cable. A separate connection to the Central Office Ground System must be used for frame
grounding purposes.
NOTE: List 8 system comes equipped with an adaptor plate for 19" to 23" mounting.
NOTE: Optional 25" and 26" mounting kits are available for 23" shelves - J438827E List 5 and List 6
respectively. Refer to Figure 5 for mounting dimensions.
Once the system has been removed from the shipping container:
Verify that the input DC voltage matches the shelves and inverters: +24 Vdc (+27 Vdc nominal) or −48 Vdc (−54
Vdc nominal).
Verify that AC voltage matches across inverters, shelves, and loads.
Install the system as follows:
1. Move the mounting brackets as required
2. Ensure there is proper clearance in the rack or shelf to install the system.
3. Put the system into position and secure with the screws located at each outside corner (four screws total).
4. Repeat steps 1 thru 3 for additional shelves, as required.
Verify the input source.
Page 16
© Copyright 2021 ABB. All rights reserved.

Advertisement

Table of Contents
loading

Table of Contents