Installing the AP
Installation flowchart
Figure 4 Installation flowchart
On a wall
Pre-installation tasks
Before installing the AP, perform the following tasks:
•
Connect the AP to a power source and the network. Examine the LEDs to verify that the AP is
operating correctly. For information about AP LEDs, see ports and LEDs in Hardware
Information and Specifications.
•
Record the MAC address and serial number at the rear of the AP for future use.
•
Make sure you have completed cabling at the installation site.
•
If the Ethernet interface rate is 2.5 or 5 Gbps, use Cat-5e or above network cables. For
information about the supported interface rates, see technical specifications in Hardware
Information and Specifications.
•
The AP is typically installed on a high position. As a best practice, access and configure the AP
before installing it.
•
If a cable is routed outdoors, make sure a lighting arrester is attached to the AP port. Prepare a
lighting arrester yourself as needed.
Start
Complete pre-installation
tasks
Determine the installation
position
Mount the AP
Connect the AP to the
power source
Connect the AP to the
network
End
1
On a ceiling