Fluid Level Check; Electrical Preparation - Sullair LS20T Operator's Manual And Parts List

Industrial air compressor 200-300 hp / 150-224 kw supervisor controller
Hide thumbs Also See for LS20T:
Table of Contents

Advertisement

Section 4
INSTALLATION
Figure 4-1 Service Air Piping (Typical)
pressor unit adapter. Therefore, it is not necessary
to check this alignment, unless high vibration is
noticed.

4.5 FLUID LEVEL CHECK

Your air compressor is also supplied with the prop-
er amount of fluid. However, it is necessary to check
the fluid level at installation. The level is checked by
looking at the sight glass located on the sump. If the
sump is properly filled, the coolant level should fill
1/2 of the sight glass when the compressor is shut-
down.

4.6 ELECTRICAL PREPARATION

Interior electrical wiring is performed at the factory.
26
Required customer wiring is minimal, but should be
done by a qualified electrician in compliance with
any applicable regional or local electrical code con-
cerning isolation switches, fuse disconnects, etc.
Sullair provides a wiring diagram for use by the
installer.
Lethal shock hazard inside.
Disconnect all power at source before opening or
servicing starter or control panel.
1. Check incoming voltage. Be sure that the incom-