Cable Connections Between Control Console And Plc Edutrainer; Establish 1-Bit Communication Connections - Festo MPS PA Operating Instructions Manual

Mixing learning system
Hide thumbs Also See for MPS PA:
Table of Contents

Advertisement

Mixing Learning System

11.5.2 Cable connections between control console and PLC EduTrainer

The cable connections are described for a control console with TP700 Comfort connected to a PLC
EduTrainer. On delivery, the cables in the control console are already connected. To remove the
connections, the front panel on the front of the control console must be removed and the cable through feed
opened on the back.
Procedure
Connect the network cable from the operator unit to the PLC controller (not shown) or check the
connection.
Check/Connect the power supply cable in the control console. The operating device is supplied via the
SysLink terminal and only switches on when the PLC EduTrainer is connected to the station and the 24 V
DC power supply unit has been switched on.

11.5.3 Establish 1-bit communication connections

The communication cables are supplied with the station and must be plugged in.
The communication connections to the other stations must be established according to the following
examples. The examples are general, but apply equally to all stations. Any deviations from this standard will
be pointed out.
Example of I/O push-in connectors between 19" frames
Figure 23: Communication connection between 19" frames
© Festo Didactic 696686
Commissioning