Table 6-7
You need to carefully check items 08 and 09 listed in
results of these two items do not meet the acceptance criteria, the UPS may be
damaged.
Table 6-7 Check items and acceptance criteria
No.
01
Issue 02 (2021-04-22)
NO TE
● When you use the NC status, remove the jumper between EPO_NC and EPO_12V first.
When you turn off the EPO switch, EPO is triggered.
● When you use the NO status, ensure that the jumper is connected between EPO_NC and
EPO_12V. When you turn on the EPO switch, EPO is triggered.
lists check items and acceptance criteria.
NO TICE
Item
Cabinet installation
Copyright © Huawei Technologies Co., Ltd.
Table
6-7. If the check
Acceptance Criteria
The cabinets are securely installed and
do not tilt due to vibration.