FLUE SYSTEM
FLUE SYSTEM
( ( Fumes duct, flue and chimney pot
Fumes duct, flue and chimney pot) )
Thsi chapter has been drawn up pursuant to European
regulations EN 13384, EN 1443, EN 1856 and EN
1457. The installer must observe both these and any
other local regulations. This manual does not in any
way substitute such regulations.
The product must be connected to a flue system which
ensures that the fumes produced by combustion are
exhausted in complete safety.
Before positioning the product, the installer must
check that the flue pipe is properly rated.
FUMES DUCT, FLUE
FUMES DUCT, FLUE
The fumes duct (which connects the hearth's fumes
(which connects the hearth's fumes
outlet with the flue) and the flue itself must, among
outlet with the flue)
other regulatory requirements:
receive the fumes from a single product (the outlets
of multiple appliances may not be conveyed into
a single flue)
be routed vertically for the most part
have no downwards sloping sections
preferably have a circular internal cross section, or
with a ratio of the sides of less than 1.5
terminate at roof level with a proper chimney pot:
the flue may not discharge directly from the wall
or into an enclosed space, even if the space in
question is open to the sky
be made of material rated fire reaction class A1 per
UNI EN 13501 or analogous national regulations.
TYPICAL CASES
46
11
49
46
INSTALLATION
be certified, with a chimney plate if metal
be of uniform cross section or vary in cross section
only immediately after the outlet, not at some mid
point of its length
THE FUMES DUCT
THE FUMES DUCT
Further to the general prescriptions for the fumes duct
and flue, the fumes duct: :
may not be made of flexible metal material
must be insulated, if routed through unheated
areas or outdoors
must not be routed through rooms in which the
installation of combustion heat generators is
prohibited, or subject to fire hazard, or which
cannot be inspected.
must enable the recovery of soot and be open for
inspection
must have at most 3 bends, through an angle of
no more than 90°
must have a single horizontal section of length
no more than 3 metri, depending on the draw.
Note in any case that long sections promote the
accumulation of dirt and are harder to keep clean.
A:
B:
46
C-E: external ambient air intake (through section of at least
D:
11
49
46
INSTALLER
insulated steel flue, pursuant to EN 1856
minimum height 1.5 m and above the level of the roof
guttering
80 cm²)
steel flue inside existing masonry chimney
13