8.1 Maintenance schedule
Intervals
Before ANY
maintenance job
Every 6 months
Whenever
necessary
8.2 Carrying out maintenance jobs
Personnel
The maintenance jobs described here may be carried out by operators, if not explicitly stated
otherwise.
Have works on electrical equipment carried out by skilled electricians, exclusively.
What must be done?
Visually check the welder and its periphery for
damage, dirt, contamination etc.
Clean, if necessary (
Check connections for tight fit.
(
See "5.4" – "5.6").
Check compressed-air supply.
(
see "5.5"
Check cooling water level?
Fill up, if necessary. (
Visually check electrode caps. If necessary, clean,
mill and/or replace. (
Check distance and –alignment of electrodes.
(
See "6.1.2".)
Check PPE for functionality. Replace, if and as
soon as necessary.
Check purity and quality of operating company's
compressed-air supply.
Check the work environment. Does it still fulfil all
the operating requirements? (
Check actual input current and voltage. Take your
own measurements.
Visually check the water separator and air filter of
the pneumatic unit. Carry out jobs as required.
(
See "8.2.2".)
Visually check the water filter. Replace, if
necessary.
(
See "8.2.3".)
Empty cooling water tank (
(
see "5.2").
Resistance Welder MULTISPOT MI-100-3
see "8.2").
See "5.2".)
See "6.1.2".)
See "9".)
see "8.2.4"). Refill
Maintenance
WHO should do
it?
Operator
Operator
Skilled electrician
Operator
43
Need help?
Do you have a question about the MULTISPOT MI-100-3 and is the answer not in the manual?