1MRS756375 T
3.
4.
5.
4.3.16
Replacing a SPA 300 series relay in 19" rack by a 615 series
IED
• Mount the IED with the mounting frame to the panel cut-out according to the
rack mounting instructions in
No modifications are needed to the panel.
615 series
Installation Manual
Mount the installation plate to the panel cut-out with M5 thread forming
screws.
2 2
1
Installation plate
Figure 39: Installation plate for replacing SPA 300 relay
Tighten the screws.
Mount the new IED.
Use a raising frame if needed.
For ordering numbers, see the ordering number table.
For replacement kit ordering numbers, see the ordering number table.
1 1
2
Torx head screw M5x10
Chapter 4.3.5 Rack mounting protection relay
Mounting
.