Floor Loading Considerations

• In the vertical mounting orientation, 60% rack space must be open at top of the product, while sides must
• If any port (RJ-45, SFP, or USB) is not used, it is recommended that such ports be covered by using the
Figure 4: Dust Caps
Floor Loading Considerations
Ensure that the floor under the rack supporting the routers is capable of supporting the combined weight of
the rack and all the other installed equipment.
To assess the weight of a fully configured routers, see the Cisco Network Convergence System 540 Small
Density Passive Cooled Routers Datasheet.
For additional information about floor loading requirements, see the GR-63-CORE, Network Equipment
Building System (NEBS) Requirements: Physical Protection document (www.telecom-info.telcordia.com).

Site Power Guidelines

The router has specific power and electrical wiring requirements. Adhering to these requirements ensures
reliable operation of the system. Follow these precautions and recommendations when planning your site
power for the router:
• The redundant power option provides a second, identical power supply to ensure that power to the chassis
• Connect each of the two power supplies to a separate input power source. If you fail to do this, your
• To prevent a loss of input power, be sure that the total maximum load on each circuit supplying the power
• Check the power at your site before installation, and periodically after installation to ensure that you are
Cisco Network Convergence System 540 Passive Cooled Small Density Routers Hardware Installation Guide
14
be free from any airflow obstructions.
dust caps that came with the product.
continues uninterrupted if one power supply fails or input power on one line fails.
system might be susceptible to total power failure due to a fault in the external wiring or a tripped circuit
breaker.
supplies is within the current ratings of the wiring and the breakers.
receiving clean power. Install a power conditioner, if necessary.