Routing Cables Out of the Cable Hole
Cut a cable hole based on the cabling mode, and route external cables through
the cable hole.
Figure 5-8 Routing cables out of the cable hole
Before connecting external cables, route the cables through the cable hole to
avoid disconnecting after installation.

5.3.1 Installing a PE Cable

Precautions
Ensure that the PE cable is securely connected. Otherwise, electric shocks may
occur.
Procedure
Step 1 Crimp an OT terminal.
● Avoid scratching the core wire when stripping a cable.
● The cavity formed after the conductor crimp strip of the OT terminal is crimped
● Wrap the wire crimping area with heat shrink tubing or insulation tape. The
● When using a heat gun, protect the equipment from being scorched.
Issue 06 (2022-03-01)
NO TICE
D ANGER
NO TE
It is recommended that silica gel or paint be used around the ground terminal after the PE
cable is connected.
NO TICE
must wrap the core wires completely. The core wires must contact the OT
terminal closely.
heat shrink tubing is used as an example.