2.3 Inspecting and unpacking the UPS cabinet

The UPS cabinet is palleted separately for shipping. The cabinet is shipped bolted to a wooden
pallet and protected with outer protective packaging material (see Figure 3-8).
CAUTION
The UPS cabinet is heavy (see Table 2-1 on page 11). If unpacking instructions are not
closely followed, the cabinet may tip and cause serious injury.
1.
Carefully inspect the outer packaging for evidence of damage during transit.
CAUTION
Do not install a damaged cabinet. Report any damage to the carrier and contact your
service representative immediately.
NOTE
For the following step. verify that the forklift or pallet jack is rated to handle the weight of
the cabinet (see Table 2-1 on page 11 for cabinet weight).
2.
Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close
as possible, before unpacking. Insert the forklift or pallet jack forks from the right side of the
cabinet, between the supports on the bottom of the pallet (see Figure 2-6 on page 14 for the
UPS cabinet center of gravity measurements).
CAUTION
Do not tilt the UPS cabinet more than 10° from vertical or the cabinet may tip over.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3 m on each side
for removing the cabinet from the pallet.
NOTE
The UPS cabinet is shipped with a debris shield covering the ventilation grill on top of the
unit. Do not remove the debris shield until installation is complete.
1027574
Revision B
UPS 450 - 550 kVA (2x225 - 2x275 kVA)
User's and Installation Guide
19

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerware 9395

Table of Contents