Introduction; Scope Of Delivery; Tools - Philips Optimus Manual

Converter test kit for optimus 50/65/80 generators release 3.x with converters 4512 104 7231x
Table of Contents

Advertisement

1

INTRODUCTION

With this document it should be possible to determine which part of kV units of an Optimus generator is still
operational and which part is defective and has to be replaced.
1.1
S
COPE OF DELIVERY
– 2 current transformers
(ratio 1:1000, 20Ω resistors at the secondary coil give a ratio of 50A primary / 1V secondary)
– Test cable with resistor
– Test cable with diode
– This documentation
1.2
T
OOLS
– Standard tools
– Extension boards C (96-pin)
– Dual trace oscilloscope with:
2 probes for signals
1 probe for external triggering
– Multimeter with diode test option
– 1 battery 1.5V D cell (R20) preferred
C cell (R14) or AA cell (R6) possible
6
Converter test kit OPTIMUS for OPTIMUS 50/65/80 gen‐
erators release 3.x with converters 4512 104 7231x
CSIP Level 1 (08.0)
© 2008 Koninklijke Philips Electronics N.V.
ALL RIGHTS RESERVED
Conv test Optimus

Advertisement

Table of Contents
loading

Table of Contents