www.ti.com
With the MCU in DFU mode, the firmware can now be uploaded through the method outlined in
4.2.1.3 GUI Setup and Usage
The GUI can be accessed from this link in either Chrome or Firefox:
INA234_236EVM_GUI/ver/1.0.0/.
4.2.1.3.1 Initial Setup
To set up the GUI the first time:
1. Make sure that the previously mentioned driver was installed successfully to ensure that everything works
properly and that the GUI can update the EVM firmware, if necessary.
2. With the EVM/SCB Controller unit plugged into the PC, go to the previously-provided GUI link.
3. To launch the GUI from the web browser, click the GUI Composer application shown in
SBOU264 – MAY 2021
Submit Document Feedback
Figure 4-3. Test Points Used to Enter DFU Mode Manually
Figure 4-4. GUI Composer Application
Copyright © 2021 Texas Instruments Incorporated
https://dev.ti.com/gallery/info/3907820/
Figure
INA234EVM and INA236EVM
Operation
Step
1.
4-4.
7