(BASED ON UNIT CONFIGURATION, SOME CHECKLIST ITEMS MAY NOT BE APPLICABLE)
1. RECEIVING AND INSPECTION
□
Unit Received Undamaged
□
Unit Arrangement/Hand Correct
□
Unit Received Complete as Ordered
□
Unit Structural Support Complete & Correct
2. HANDLING AND INSTALLATION
□
Unit Mounted Level & Square
□
Proper Electrical Service Provided
□
Proper Service Switch/Disconnect Provided
□
Proper Access Provided For Unit & Acces-
sories
□
Proper Overcurrent Protection Provided
□
Proper Chilled Water Line Size to Unit
□
Proper Hot Water Line to Unit
□
All Services to Unit in Code Compliance
□
All Shipping Screws & Braces Removed
3. COOLING/HEATING CONNECTIONS
□
Protect Valve Package Components From
Heat
□
Connect Field Piping to Unit
□
Install Drip Pan as Required
□
Install Condensate Pan Under Piping as
Required
□
Mount, Secure, and Support Valve Packages
□
Pressure Test All Piping for Leaks
□
Insulate All Piping as Required
□
Connect Supply and Return Pipe to Correct
Coil Connections
4. DUCTWORK CONNECTIONS
□
Install Ductwork, Fittings & Grilles as Required
□
Proper Supply/Return Grille Types & Sizes
Used
□
Insulate All Ductwork as Required
32
INSPECTION & START-UP CHECKLIST
5. ELECTRICAL CONNECTIONS
□
Refer to Unit Wiring Diagram
□
All Field Wiring in Code Compliance
□
Connect Incoming Power Service or Services
□
SCR Fan Speed Control Wired to Low Speed
□
Tighten All Electrical Connections Prior To
Start-Up
6. UNIT STARTUP
□
General Visual Unit & System Inspection
□
Record Ambient Temperature
□
Close All Unit Isolation Valves
□
All Ductwork & Grilles in Place
□
Start Fans, Etc.
□
Check All Ductwork & Units for Air Leaks
□
Record All Final Settings for Future Use
□
Check All Dampers for Proper Operation
□
Verify Proper Heating Operation
□
Verify Proper Cooling Operation
□
Record Electrical Supply Voltage
□
Check All Wiring for Secure Connections
□
Vent Water Systems as Required
□
All Unit Panels & Filters In Place
□
Check for Overload Condition of All Units
□
Balance Air Systems as Required
□
Check Piping & Ductwork for Vibration
□
Verify Proper Cooling Operation
□
Reinstall All Covers & Access Panels