Actuator Test Run; Underfloor Heating Screed Dryout - Daikin Altherma 3 H MT F Installer's Reference Manual

Hide thumbs Also See for Altherma 3 H MT F:
Table of Contents

Advertisement

11
|
Commissioning

11.4.4 Actuator test run

11.4.5 Underfloor heating screed dryout

About underfloor heating screed dryout
Installer reference guide
214
Purpose
Perform an actuator test run to confirm the operation of the different actuators.
For example, when you select Pump, a test run of the pump will start.
To perform an actuator test run
Conditions: Make sure all operation is disabled. Go to [C]: Operation and turn off
Space heating/cooling and Tank operation.
1 Set the user permission level to Installer. See
user permission
level" [
2 Go to [A.2]: Commissioning > Actuator test run.
3 Select a test from the list. Example: Pump.
4 Select OK to confirm.
Result: The actuator test run starts. It stops automatically when
ready (±30 min).
To stop the test run manually:
1 In the menu, go to Stop test run.
2 Select OK to confirm.
Possible actuator test runs
Backup heater 1 test
Backup heater 2 test
Pump test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
Shut off valve test
Diverter valve test (3-way valve for switching between space heating and
tank heating)
Bivalent signal test
Alarm output test
C/H signal test
DHW pump test
Purpose
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
"To change the
4
 117].
EPRA08~12EAV3+W1 + ETVZ12S18+23EA6V+9W
Daikin Altherma 3 H MT F
4P634887-1 – 2021.03

Advertisement

Table of Contents
loading

Table of Contents