Preparing To Start The Pump - Deep Well - STA-RITE ALB Owner's Manual

Convertible deep well jet pumps
Table of Contents

Advertisement

Available languages

Available languages

Preparing to Start the Pump – Deep Well
Open control valve
as far as possible
and fill pump and
piping through
priming port
or priming tee.
280 0395
Figure 12: Fill Pump
556 0395
Figure 13: Prime Pump
A-Open Control Valve
B-Watch for Pressure Gauge to Flutter
C-Close Control Valve until Pressure
Stabilizes
Figure 14: Set Control Valve
water inside pump, causing hazardous pressure in unit, risk of explosion
and possibly scalding persons handling pump.
pump to overheat, damaging seal and possibly causing burns to persons
handling pump. Fill pump with water before starting.
Step 1. Open the control valve as far as possible (see Figure 12). Then
Step 2. Replace all fill plugs and close the control valve completely
Step 3. Power on! Start the pump and watch the pressure gauge. The
Step 4. After 2 or 3 minutes, the gauge should show pressure. If not, stop
Replace all
fill plugs and
close control
valve completely.
Step 5. When pressure has built up and stabilized at about 50 PSI, slowly
Step 6. After the pump has built up pressure in the system and shut off,
Step 7. (PL Series pumps only). Check for leaks around band clamp. If
NOTICE: Due to normal irregularities in the cup seal leather and the inner
walls of the casing, packer jets do not form a perfect seal. In a dormant sys-
tem, pressure will leak off over time, causing pump to cycle periodically to
maintain system pressure level.
281 0395
Never run pump against closed discharge. To do so can boil
Never run pump dry. Running pump without water may cause
remove the priming plug from the pump and fill the pump, fill all
piping between the pump and the well, and make sure that all
piping in the well is full. If you have also installed a priming tee in
the suction piping, remove the plug from the tee and fill the suction
piping.
(Figure 13).
pressure should build rapidly to 50 PSI as the pump primes.
the pump, remove the fill plugs, reopen the control valve, and refill
the pump and piping. You may have to repeat this two or three
times in order to get all the trapped air out of the piping. Don't for-
get to close the control valve each time before you start the pump.
open the control valve (see Figure 14) and let the pressure drop
until the pressure gauge needle starts to flutter. When the needle
flutters, close the valve just enough to stop the flutter (see Figure
14). Your pump is now operating at its most efficient point.
check the pressure switch operation by opening a faucet or two and
running enough water out to bleed off pressure until the pump
starts. The pump should start when pressure drops to 30 PSI and
stop when pressure reaches 50 PSI. Run the pump through one or
two complete cycles to verify correct operation. This will also help
clean the system of dirt and scale dislodged during installation.
pump is leaking, tighten clamp nut 1-2 turns. Do not overtighten.