Phase 2
N4
ROCK BOARD - W4L12499
5/8"x2 3/8"x27 3/4" (16x60x706)
(x1)
M14
ROCK BOARD - W4L12497
5/8"x3 3/8"x27 3/4" (16x86x706)
(x4)
PREPARATION: INSTALL T-NUTS
M13
ROCK BOARD - W4L12496
5/8"x3 3/8"x27 3/4" (16x86x706)
(x8)
M15
ROCK BOARD - W4L12498
5/8"x3 3/8"x27 3/4" (16x86x706)
(x4)
IT CAN HELP TO SET ALL THE
BOARDS IN PLACE TO MAKE
SURE THEY MATCH THE
DIAGRAM PRIOR TO MOUNTING
THEM WITH THE PROVIDED
SCREWS.
71
H100398
(x24)
H100200
(x68)
USE THE FOLLOWING REPEATING PATTERN TO
BUILD THE ROCKWALL. BEGINNING AT THE TOP
THE PATTERN IS M13, M15, M13, M14. REPEAT 4
TIMES AND END WITH N4 BOARD. MAKE SURE TO
PLACE EACH M14 BOARD SO THE HOLES
ALTERNATE RIGHT TO LEFT OF CENTER.
THESE SHOULD LINE UP
WHEN PROPERLY ASSEMBLED.
CENTER LINE
NOTE EVENLY SPACE ALL GAPS.
T-NUT BLK
1/4
SCREW PFH BLK
8x1 1/2