Basic Operations
2. Select [PARALLEL SETUP] to enter the parallel setting interface.
3. Press the Up and Down key to select the "Operating Mode" > "Parallel".
4. Set "Phase Class" as "A+B+C".
5. Set "Phase/Position" of each unit as "Slave-B(2)" and "Slave-C(3)".
6. Press [Enter] to save the setting.
Select one electronic load as the master.
1. Press [Menu] to enter the system menu setting interface.
2. Select [PARALLEL SETUP] to enter the parallel setting interface.
3. Press the Up and Down key to select the "Operating Mode" > "Parallel".
4. Set "Phase Class" as "A+B+C".
5. Set "Phase/Position" as "Master-A(1)".
6. Set "Total Unit" as 3.