Installation
5.3.2
Cleaning the pipeline
We recommend additionally flushing the
pipeline without the installed regulator be-
fore start-up. In this case, install a suitable
length of pipe into the pipeline in place of
the regulator.
Î Observe the mesh size of the upstream
strainer for the maximum particle size.
Use strainers to suit the process medium.
Î Check the strainer for dirt each time the
pipeline is flushed and clean it, if neces-
sary.
5-8
5.4 Testing the regulator
DANGER
!
Risk of bursting due to incorrect opening of
pressurized equipment or components.
Regulators and pipelines are pressure equip-
ment that may burst when handled incor-
rectly. Flying projectile fragments or the re-
lease of process medium under pressure can
cause serious injury or even death.
Before working on the regulator:
Î Depressurize all plant sections concerned
and the regulator.
Î Disconnect the control line.
Î Drain the process medium from all the
plant sections concerned as well as the
valve.
Re
DANGER
!
Risk of personal injury due to process me-
dium escaping.
Î Do not start up the regulator until all
parts have been mounted.
WARNING
!
Risk of hearing loss or deafness due to loud
noise.
Noise emission (e.g. cavitation or flashing)
may occur during operation caused by the
process medium and the operating condi-
tions.
Î Wear hearing protection when working
near the valve. Follow the instructions
given by the plant operator.
EB 3132-3 EN