Fixing the Machine in Place
6.3

Machine Installation

Select the anchoring method to suit the local conditions.
The usable plug length (1) must be at least 184 mm (7.21 in).
Work steps:
§ To level the machine, slide the slotted leveling plates (7) included with the machine between
the trough and floor.
Attention:
For the legally stipulated floor clearance of the safety trough, you must
also install the supplied spacer plates (6) between the trough and floor.
§ Put the attaching plug (2) through the trough pipe (5) (only for the
safety expansion anchor)
§ Mount the washers, spring washers and nuts.
§ Tighten the nuts on the anchor evenly.
Part numbers:
Leveling plates:
Spacer plates:
25
25
1 mm SN 709955
2 mm SN 709954
3 mm SN 709909
8 mm SN 709902
1 Usable plug length
2 Attaching plug
3 Washer, spring washer and nut
4 Tank
5 Trough pipe
6 Spacer plate
7 Leveling plates