Fixing the Machine in Place
Adhesive plugs/shear connectors
Steps:
§ Position the machine in its intended position. Note the transport information in Chapter 4.
Use the holes of the machine trough as a drilling template.
§ Prebore with 16 mm (.6 in) stone drill. Drill in vertically!
Remove the machine or angle bracket.
§ Boreholes:
Drill the diameter and depth according to the information provided
by the plug manufacturer and blow out any dust.
For further steps, refer to the information provided by the plug manufacturer.
Note the hardening time.
Position the machine and level.
If the floor is uneven, level the machine with leveling plates and even out the surface with
filler (epoxy resins).
Finish the machine installation according to Point 6.3.