ADTEK AEM-DRB Operation Manual page 44

Multi circuit power meter(din rail)
Table of Contents

Advertisement

Chapter 5 Message of Abnormal Operations
5.1 Common malfunction analysis
5.1.1 Power meter dosen't work after it's electrified
• Make sure voltage and other wiring is correct, voltage should be in the future functional
range.
• Turn off meter and restart.
5.1.2 Voltage or current reading in incorrect
• Check the wiring mode settings match the actual wiring mode.
• Check the voltage potential transformer (PT) and current transformer (CT) variable ratio
are set correctly.
• Check the GND is correctly grounded.
• Check the voltage potential transformer (PT) and current transformer (CT) are intact.
5.1.3 Power or power factor reading is incorrect,
• Compare the voltage and current input of the inter-wiring and wiring diagram to check
whether the phase relationship is correct.
5.1.4 RS-485 communication is unusual
• Check the communication baud rate, ID and communication protocol setings of the upper
machine are consistent with the meter.
• Please check whether the data bit, stop bit, check bit settings are consistent with the host
computer.
• Check if RS-485 converter is working.
• Check whether there is any problem with the entire communication line (short circuit,
open circuit, grounding, whether the shield wire is correctly grounded at single-end, etc.).
• Turn off the meter and host computer, and then restart.
• For long communication lines, it is recommended that a matching resistance of about 120
ohms be connected in parallel at the end of the communication line.
but voltage and current are correct
40

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AEM-DRB and is the answer not in the manual?

Table of Contents