On the Primary unit set DIP switch 1 on (position 1) and keep 2 off (position 0).
On the Replica unit keep DIP switch 1 off (position 0) and set 2 on (position 1).
All other DIP switches (3...8) on the Replica unit must match the settings on the Primary unit. For an overview of DIP switch
settings, please see the user manual.
4.7

Initial start-up

1. Install the DC fuses and close the battery switch.
2. Close the covers of all units.
3. Close the AC breaker in AC output 1 of each unit.
4. Switch on all units.
5. Check that the units are working properly.