Table 5: Cables supplied with 5U84 storage enclosure

Description
Power cables mains C19-
C20 R/A
Note
Lyve Rack provides C13-C14 power cords.

Table 6: Cables supplied with servers

Description
Power cables mains C13-
NEMA 5-15.
Depending on regional
server accessories, the
power cords supplied may
be different than shown.

6.2 | Recommended cabling sequence

The following is the suggested cabling sequence. Make sure the cables are connected to the correct
port as shown in Figure 9.
Cable Server A SAS interface to Controller A using 11a and 11b.
1.
Cable Server A SAS interface to Controller B using 11c and 11d.
2.
Cable Server B SAS interface to Controller B using 12a and 12b.
3.
Cable Server B SAS interface to Controller A using 12c and 12d.
4.
Cable Server A Management Interface Cable to Management Switch using 4a.
5.
Cable Server B Management Interface Cable to Management Switch using 4b.
6.
Cable Server A BMC Interface Cable to Management Switch using 5a.
7.
Cable Server B BMC Interface Cable to Management Switch using 5b.
8.
Cable Private Data Interface Server A to Server B using 10.
9.
Using a QSFP28 Y cable or two 100GbE to 100GbE QSFP28 cables:
10.
Image
Image
Lyve Rack R1 Installation Guide
Quantity
2
Quantity
2 in each server kit for a total of
4
18

Advertisement

Table of Contents
loading

Table of Contents