8 | Turn ON power
Note
Please ensure that all equipment is connected to the appropriate power sources
before starting the powering ON sequence.
8.1 | Switch ON storage enclosure
To switch ON the 5U84 storage enclosure:
•
Switch ON the power on both PSUs using Power Switches (see
Note
It is not required to switch ON both PSUs simultaneously. However, it is
recommended to switch ON PSU 0 followed by PSU 1.
Figure 16: 5U84 storage enclosure PSU. Power switch 'O' = OFF; 'I' = ON
Wait for five minutes to complete initialization and self-test functions. Then verify that the 5U84
storage enclosure front panel LEDs are illuminated as shown in
Lyve Rack R1 Installation Guide
Figure
Figure 17
34
16).
and
Figure
18.