Server Installation; Figure 7: Populated The Top Drawer; Figure 8: Populated The Bottom Drawer - Seagate Lyve Rack R1 Installation Manual

Hide thumbs Also See for Lyve Rack R1:
Table of Contents

Advertisement

a. Ensure anti-temper locks of the top drawer are unlocked using the supplied T20
screwdriver.
b. Using drawer latches, push both latches of the same drawer towards the center of the
drawer.
c.
Slowly pull top drawer towards yourself.
d. Insert all DDICs starting from top drawer with drives at the front left of each row leaving
no empty drive slots paying attention to inserting drives in ascending order.
e. Repeat until all rows on the top drawer are full. Visually re-check that the DDIC sequence
numbers match the figure.
f.
Close the drawer and lock it.
g. Repeat the steps a through f for the bottom drawer.

Figure 7: Populated the top drawer

Populate the top drawer first. Close and lock the
drawer.
8.
The anti-tamper locks do not have to be used. If they are used to lock the drawer, store the T20
screwdriver safely afterwards. Now that all DDIC and rear modules are inserted, the rack
installation can progress to the next stage.

5.4 | Server installation

Depending upon your server configuration, follow instructions provided in the Server Installation
chapter of
S
S
UPERMICRO
UPER
unpack and install the servers into the rack.
Refer to
above. The servers are not configured identically. Hence, you must first identify
Figure 2
server B box and rack the server directly above the 5U84 storage enclosure. After racking server B,
identify server A box, and rack it directly above server B.
S
U
6019P-WTR
ERVER
SER MANUAL
Lyve Rack R1 Installation Guide

Figure 8: Populated the bottom drawer

Populate the bottom drawer after filling and
closing the top drawer. Close and lock the
drawer.
S
S
S
OR
UPERMICRO
UPER
ERVER
14
to
U
6019U-TRT
SER MANUAL