25. START-UP / COMMISSIONING: PER LOCAL & NATIONAL CODE REQUIREMENT
THIS EQUIPMENT HAS BEEN FACTORY FIRED AND TESTED PRIOR TO
SHIPMENT. HOWEVER, THIS APPLIANCE REQUIRES COMMISSIONING AND
FIELD ADJUSTMENT / SPECIFICATIONS CONFIRMATION TO ENSURE SAFE
AND EFFICIENT OPERATION.
PROJECT NAME:
Area / Bldg:
Project Location:
Contractor:
Address:
City:
Phone:
Commission Date:
Project Heater Number / Identifier:
Heater Model Number:
Heater Serial Number:
TO ENSURE THAT SITE CONDITIONS ARE COMPATIBLE WITH THE HEATER'S PER-
FORMANCE AND TO ALLEVIATE NUISANCE CALL-BACKS, THE FOLLOWING START-
UP NEEDS TO BE COMPLETED BY THE QUALIFIED GAS INSTALLER.
A TECHNICIAN CALLING FOR TECHNICAL SUPPORT MUST PROVIDE THE
INFORMATION FROM THE COMPLETED COMMISSIONING REPORT ON
FAX COMPLETED REPORT TO TECHNICAL SERVICES:
WARNING
During start up, material coatings used in the production process of tubes and reflectors will
"burn off" and create smoke during the first hour of operation. This is temporary and normal.
Please ensure that there is sufficient ventilation to adequately clear the smoke from the space.
Notify site and safety personnel to ensure that alarm systems are not unduly activated.
STS-JZ-F / IQ-F I&O Manual Z83.20-2016
IM101220
RD: APR 2019
RL: 20C
THE NEXT PAGE
FAX 1-866-361-0523,
VOICE 1-877-446-3727
START UP 'SMOKE'
50
State / Prov:
Cell #:

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents