18.1 SPECIAL TUBE CONNECTION: 100,000 Btuh x 20 ft ONLY
NOTE: The connection of 1ST & 2ND tubes of the 100,000 x 20 ft heater experiences
strong forces of expansion. Follow instructions below for special coupling of the tubes and
orientation of the turbulator in the 2nd tube..
SPECIAL COUPLER INSTALLATION
1. Install first tube so that the welded seam
along the tube length is in the lower half of
the tube facing downward
2. Slide the loosened tube coupler on to the
first tube, past the swage
3. The second tube is supplied with a ¼" hole
in the tube at the female end.
4. Slide second tube over swaged end of first
tube so that ¼" hole is located 90° up from
the bottom (3 or 9 o'clock position)
5. Note that the spine of the turbulator should
be oriented in a vertical position
6. Through the existing ¼" hole , drill a ¼"
hole through the wall of the first tube
7. Insert ¼" rivet into the hole
8. Slide coupler into position – half onto each
tube – covering the rivet head
9. Tighten coupler bolts to 40 ft-lb
10. Install reflectors
Step 5
100,000 Btuh x 20 ft Heater
NOTE:
TURBULATOR ORIENTATION
Install tube with turbula-
tor spine in vertical posi-
tion for best performance
VIEW INSIDE TUBE: Ensure the 8 ft (2.4 m) tur-
bulator installed in the second tube is oriented
with its spine in a vertical position, and located at
the vent end of the tube.
This will result in the best performance and radi-
ant output from the system.
STS-JZ-F / IQ-F I&O Manual Z83.20-2016
IM101220
RD: APR 2019
RL: 20C
TOOLS REQUIRED:  Electric Drill
2 ft
with 8 ft turbulator
36
 1/4" Drill Bit (supplied)
FIGURE 18 SPECIAL COUPLING:
100,000 x 20 ft
- Fasten Second Tube to First Tube -
Step 1
Steps 2
thru 6
Step 7
Steps 8
& 9
Welded seam in lower
half of tube, facing
downward
1/4" Rivet