Solar Panel - Centurion LEVER4 Installation Manual

Swing gate operator
Table of Contents

Advertisement

12.16 Solar Panel

TO SECOND
SOLAR PANEL
(IF FITTED)
SOLAR PANEL
X (NOTE1)
ANGLE, X °
30°
JOHANNESBURG
40°
PE & EAST LONDON
45°
NOTE: TO PREVENT THE STATUS LED ON THE CP77 CONTROLLER FROM INDICATING
"MAINS FAILURE", IT IS NECESSARY TO CONNECT TERMINAL 13 TO TERMINAL 15.
13.0 COMMISSIONING
13.1 Applying Mains Power
OPTION 1
CP13E
POWER SUPPLY
E
N
220V AC
L
SUPPLY
OPTION 2
SOLAR REGULATOR
(WITH LOAD SHED)
BLACK
RED
0,5mm²
CABLE MIN
LOCATION
e.g. PDI 120505L-3.5DC
CAPE TOWN
220V AC SUPPLY TO GATE
- APPLY 220V AC POWER
- CHECK POWER ON INDICATION
15V AC
TO CONTROLLER
E
N
L
PLUG IN
CONNECTOR
LOW VOLTAGE SUPPLY TO GATE
- PLUG IN TRANSFORMER AND SWITCH ON CIRCUIT
- CHECK POWER ON INDICATION
15V AC
TO CONTROLLER
TYPE WITH LOAD SHED
POWER CABLE 2.5mm² MINIMUM
SENSE CABLE 0.2mm²
NOTE 2
2
1
NOTE 2
SENSE CABLE 0.2mm²
POWER CABLE 2.5mm²
19
19
LOAD e.g. FLUORESCENT
LIGHT 12V DC
CP77
x x
CONTROLLER
GREEN = POWER SUPPLY
CONNECTED
AND SWITCHED ON
CP77
x x
CONTROLLER
GREEN = POWER SUPPLY
CONNECTED
AND SWITCHED ON
- -
+
BATTERY
DEEP CYCLE

Advertisement

Table of Contents
loading

This manual is also suitable for:

Lever5Lever4smaLever4dmaLever5smaLever5dma

Table of Contents