Summary of Contents for Holzhof MAX XM 100 RAP

  • Page 1 MAX XM 100 RAP line assembly instructions...
  • Page 2 TIME SEQUENCE TO BE FOLLOWED: 1. STRUTS AND PLATFORMS 6. BENCH 2. ARCHWAYS 7. ATTACHED SWING 3. PARAPETS 8. ATTACHED GYM 4. SLIDE 9. ROOF 5. CLIMBING BOARD 10. UNDERGROUND LAYING/ANCHORAGE OF STRUCTURE...
  • Page 3 NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the Article fixing CODE N. NAME num. correct positioning of the elements has been xpe11 Shaped PE nut protection cap verified. xpe10 PE nut protection cap xpe116 PE cap ISO7089 Ø8 washer...
  • Page 4 NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified. 1. Position the archway between the struts and fix it by inserting: 1 x M8 washer (3), 1 x M8x260 TORX screw (2), 1 x Ø25 mm.
  • Page 5 NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified. 1. Position the PE parapet between the struts, resting the two lower fixing wings on the platform and then fix using: 4 x M8 washer (3) 4 x M8x80 TEL screw (2) WOOD...
  • Page 6 1. After having fixed the PE archway (2), place the body of the curved Article num. Default/ NAME Quantity slide (3) on the platform of the tower (1) and insert the bolts, necessary for fixing, into the holes present on the slide (3). Aladin tower 2.
  • Page 7 NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified. 1. Insert the (5) M8x70 threaded bars into the bushes present on the (6) climbing board. 2.
  • Page 8 1) PE cap (4x) 2) PE nut protection cap (4x) 3) M8 washer (4x) 4) M8x130 TEL screw (4x) LG* 5) M6 3x60 TEFR screw (4x) AL* 6) Assembled bench NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified.
  • Page 9 Article Default/ CODE N. NAME num. Quantity PE roof xpe10 PE nut protection cap xpe116 PE cap IS07089 Ø8 washer M8x80 TEL screw BOLTS AND SCREWS: wood: M8x80 TEL SCREW aluminium: M6,3x60 TEFR SCREW NOTE: The models represented are purely indicative.
  • Page 10 Proceed with fixing, following the instructions illustrated in the next pages. 2) Fix the beam to the structure strut 4) Fix the flower-shaped gable board in 1) Fix the struts to the beam 3) Fix the swing, which can be the plank, cage or palm type NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps...
  • Page 11 Article num. Quantity CODE N. NAME M10X120 HEX SCREW 10X110 CUP SQUARE SCREW XPE116 PE CAP Ø10 WASHER XPE11 SHAPED PE NUT PROTECTION CAP XPE10 PE CAP M10 SELF-LOCKING NUT 1. Attach the struts to the beam using the relevant bolts as indicated in the figure.
  • Page 12 1. Fix the swing beam to the structure strut using: 1) 4 x PE nut protection cap 2) 4 x M8 washer 3) 2 x M8x115 Hex Screw 4) 4 x PE cap 5) 2 x M8 Self-locking nut NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified.
  • Page 13 Article num. Quantity NAME Assembled swing body UNI4017 M8X25 HEX SCREW UNI7473 M8 self-locking nut 1. Attach the assembled swing body to the beam, introducing the bolts necessary for fixing into the swing hangers, as indicated in the figure. NOTE: colours and models represented are purely indicative. The following instructions can also be applied to swings with iron beams.
  • Page 14 Article Quantity CODE N. NAME num. XPE116 PE CAP M8X80 HEX SCREW OR M6,3X60 SELF-TAPPING SCREW 08 WASHER XPE10 PE NUT PROTECTION CAP XPE174 ROTATIONALLY-MOULDED GABLE BOARD IN PE Wooden struts: Aluminium struts M8x80 TEL SCREW: M6,3x60 SELF-TAPPING SCREW 1. Fix the gable board (5) to the struts using the relevant bolts as indicated in the figure and repeat the operation on the opposite side and for the second gable board.
  • Page 15 1. Position the climbing net beam (3) in the housing of the pre- assembled climbing ladder (4), inserting the bolts necessary for fixing as in the figure, however without fixing it completely and without positioning the caps. NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been verified.
  • Page 16 1) 1 x climbing net strut 2) 1 x rope beam 3) 1 x net beam 4) 1 x climbing ladder 5) 4 x M8x80 TEL SCREW 6) 3 x M8x110 HEX SCREW 7) 4 x PE nut protection cap 8) 6 x shaped PE nut protection cap 9) 10 x M8 washers 10) 3 x M8 self-locking nuts...
  • Page 17 1. Position the upper part of the climbing net (1), inserting the bolts necessary for fixing into the thimbles as indicated the figure, without fixing it completely and without positioning the caps. 2. Position the climbing rope (6), inserting the bolts necessary for fixing into the thimbles as indicated the figure, without fixing it completely and without positioning the caps.
  • Page 18 NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the UNDERGROUND correct positioning of the elements has been verified. ANCHORAGE climbing rope - climbing rope - 1. Drill. 2. Clean the hole thoroughly using an air pump and small brushes.
  • Page 19 Concrete deck rubber safety flooring...
  • Page 20 1. Excavate a hole with diameter of 30 cm and depth of 60 cm 2. Cast a first layer of concrete with thickness of 10 cm.
  • Page 21 3. When the concrete has set, position the slide bracket in the excavation hole, checking the correct alignment of the lower part of the slide with the finished ground level.
  • Page 22 4. Complete concrete casting as per layout. 5. When the concrete has set, fill the excavation hole by compacting the infill material up to the finished ground level.
  • Page 23 1. Attach the brackets (1) by introducing the following in sequence: PE nut protection cap (2), M8 washer (3), M8x25 HEX screw (4), PE cap (5) 1. Excavate two holes with diameter of 30 cm and depth of 60 cm NOTA BENE: it is recommended to fix the bolts definitively and only insert the caps once the correct positioning of the elements has been...
  • Page 24 1. Cast a first layer of concrete with thickness of 5 cm in the previously realised excavation hole (see the next page for dimensions). 5 cm concrete slab 2. Complete concrete casting as per layout. 3. When the concrete has set, fill the hole by compacting the infill material up to the finished ground level.
  • Page 25 sand bark mulch ne gravel BRACKET 100 cm.
  • Page 26 land scarification rubber safety flooring 4.5 cm. — concrete slab 7.5 BRACKET 75 cm.
  • Page 27 1. Drill. 2. Clean the hole thoroughly using an air pump and small brushes. 3. Insert the anchor into the hole present on the bracket with the aid of a hammer. 4. Tighten using dynamometric wrench. rubber safety flooring 4 x M10x90 screw anchors...
  • Page 28 Article num. Quantity CODE N. NAME xfe265 59x59x35 stainless steel angle bracket xpe10 PE nut protection cap xpe116 PE cap M10 self-locking nut M8x115 screw anchor Ø10 washer 1. Position the slide on the support surface, marking the position of the screw anchor.
  • Page 29 Article Quantity CODE N. NAME 1. Position the climbing board on the support surface and mark the num. position of the screw anchors. xpe10 PE nut protection cap 2. Drill the support surface and position the screw anchors. xpe116 PE cap 3.
  • Page 30 1. Drill. 2. Clean the hole thoroughly using an air pump and small brushes. 3. Insert the anchor into the hole present on the bracket with the aid of a hammer. 4. Tighten using dynamometric wrench. 4 x M10x90 screw anchors...