7. Install the LP pilot orifice following the instructions below.

(a) Use a 7/16" open-end wrench to remove the pilot hood.
(b) Remove and discard the Natural Gas (NG) orifice. Place the LP orifice in the pilot assembly then replace
the pilot hood, tightening the pilot hood until it is snug (do not over-tighten).
8. Remove the control panel to access the gas control panel. The stepper motor (adjustable
regulator) has an installation sheet included with it – make sure to follow all of the directions.
Place the stepper motor on the gas control valve (see Figure 1) – MAKE SURE IT IS
CORRECTLY ORIENTED. Secure using the screws included with the motor (see Figure 2) –
tighten to 25 Lb-inches. Leak test this area after installation to verify proper installation.
9. Replace the firebox components. Install the logs and embers. Replace the glass.
10. Make the gas line connection, bleed the gas line (if applicable), start the heater, and thoroughly leak-
test all gas connections and the gas control valve.