Servicing
9.1 Preparing the valve for

service work

1. Lay out the necessary material and tools
to have them ready for the service work.
2. Put the regulator out of operation (see
the 'Decommissioning' section).
Tip
We recommend removing the regulator from
the pipeline before performing any service
work (see the 'Removing the regulator from
the pipeline' section).
The following service work can be per-
formed after preparation is completed:
− Change set point range (see section 9.4)
− Clean and exchange the seat and plug
(see section 9.5)
9-4
9.2 Installing the regulator
after service work
Î Put the regulator back into operation (see
the 'Start-up' section). Make sure the re-
quirements and conditions for start-up or
putting the valve back into operation are
met.
9.3 Service work
Î Before performing any service work,
preparations must be made to the regu-
lator (see section 9.1).
Î After all service work is completed, check
the regulator before putting it back into
operation (see 'Testing the regulator' in
the 'Installation' section).