Commissioning
WARNING: Silent pump cannot be dry run for extended period.
1
Ensure all items on the below checklist have been ticked off prior to commissioning.
This is a gravity system product, do not install on a mains pressure system.
Ensure product is installed in a recommended orientation.
Ensure pipework is completely free of airlocks & dead legs.
Ensure pipework is flushed & isolators are turned on.
Ensure supplies are correctly plumbed, are on & tanks full.
Ensure handset is removed, hose dropped & directed to waste.
The remote on/off button will not operate until commissioning has been completed.
2
Turn on the water supply and open water inlet supply isolators.
(Applies to Pumped Valve only)