4.6.3 Installation of the large bottom contact (N1=6) in the transformer

Overview
The end-shield can be installed to both the large bottom contact and the bottom nut of the bushing. This
procedure describes installation on the bottom contact. For installation on the bottom nut, refer to Installation
of the small bottom contact in the transformer, page 35.
41
Large bottom contact
Procedure
1.
Install the springs (15), the guiding sleeves (16),
the pressing ring (17), and the hex screws (18) to
the top of the bottom contact.
Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
Torque
40 Nm