Activating Screed Drying; Leak Test On Balanced Flue System (Annular Gap Check) - Viessmann Vitodens 100-W B1HF Series Installation And Service Instructions Manual

Wall mounted gas condensing boiler
Table of Contents

Advertisement

Commissioning, inspection, maintenance
Adjusting pump rate of integral circulation pump
Curve
Pump rate of circulation pump
A
B
C
D
E
F
G
H
K
L

Activating screed drying

Screed drying
Six different temperature profiles can be set for screed
drying:
Default temperature profiles can be set in "System
configuration".
For further details, see "Function description".

Leak test on balanced flue system (annular gap check)

A
Fig. 29
Combustion air aperture
A
For balanced flue systems tested together with the
heat generator, there is no requirement for a tightness
test (overpressure test) during commissioning by the
flue gas inspector.
In this case, we recommend that a simple tightness
test is carried out during system commissioning. For
this, check the CO
or O
2
2
tion air at the annular gap of the balanced flue pipe.
44
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
100 %
concentration in the combus-
(cont.)
Note
Screed drying applies to all connected heating circuits
simultaneously. DHW heating is not possible during
screed drying.
If the CO
concentration is less than 0.2 % or the O
2
concentration is greater than 20.6 %, the flue pipe is
deemed to be sufficiently gas-tight.
If actual CO
values are greater or O
2
then pressure test the flue pipe with a static pressure
of 200 Pa.
2
values are lower,
2