5 Commissioning the drive

1.
Carefully read the safety instructions in the Safety chapter of the Vacon 100
installation manual.
2.
After installation, but before the power is turned on, check that:
a.
the inverter and motor are earthed;
b.
the power supply and motor cables comply with the requirements of the
installation instruction manual; see Chapter 4 of the installation manual for
more on this (the motor cables and control cables must comply with the EMC
requirements, and the shielding must be earthed on both sides);
c.
the cable routing of the control cables is separated from the power cables, and
that the shielding of the cables is earthed. During installation, the wires may
not touch any electrical components of the frequency converter;
d.
check the switch setting of the analogue inputs and outputs.
3.
Check the quality and quantity of the cooling air.
4.
Check for any condensation inside the frequency converter.
5.
Check that all Start/Stop switches on the I/O terminals are in the Stop position.
6.
Connect the frequency converter to the mains.
7.
Set the parameters (see Application Manual). Note; Enter all rated motor data
according to the rating plate of the motor used.
8.
Conduct a functional test before the motor is connected to the regulator.
Conduct test a.:
Vacon 100 Flow
22