LEVEL 2 – SIX MONTHLY TESTS
The Level 2 tests shall consist of all the inspection and testing procedures specified
in the previous clause and the following. These shall be carried out every 6 months.
(a)
Visually check the installation, location and siting of all equipment against the
system installation records. Record and report any discrepancy found
between the site records and the actual installation.
(b)
Check battery float charge voltage and current. These should be within
specified tolerances.
(c)
Carry out level 1 maintenance procedure as described in section 6.1
(d)
Disconnect the a.c. mains and measure the standby battery voltage under full
load conditions. The battery voltage shall be not less the 95% of the nominal
voltage. If less than 95% of the nominal voltage, the battery shall be tested
and / or replaced.
(e)
Reconnect the a.c mains and measure the current from the battery charger.
This current shall be within specified tolerances.
(f)
Measure and record the audible sound level in each zone. Check that it is in
accordance with previous measurements.
(g)
If visual warning lights are installed, check that they operate, and that the
flash rate is between 60 and 120 flashes per minute.
(h)
Record the completion of tests in the logbook, noting any defects and
remedial action required. Ensure the owner signs the report.