Download Print this page

Eaton Cutler-Hammer QS4500TE0001 Quick Start Instructions

Athi/atvi

Advertisement

Quick Links

Cutler-Hammer
QS4500TE0001
ATHI/ATVI QUICK START INSTRUCTIONS
!
WARNING
THIS INSTRUCTION IS NOT A COMPLETE SOURCE
OF INFORMATION ON THE TRANSFER EQUIP-
MENT. INSTALLATION SHOULD NOT BE STARTED
UNTIL THE ENTIRE INSTRUCTION BOOK HAS
BEEN REVIEWED AND UNDERSTOOD. FAILURE TO
FOLLOW INSTRUCTIONS CAN RESULT IN DEATH,
SEVERE PERSONAL INJURY, OR PROPERTY
DAMAGE.
Step 1: Mount the transfer switch on a flat rigid surface
(Figure 1). Shim if necessary. For seismic mounting
requirements, check the instruction book.
A
See Detail
A
View
Shim If Necessary
Figure 1 Mounting Details
Effective June 2001

Advertisement

loading

Summary of Contents for Eaton Cutler-Hammer QS4500TE0001

  • Page 1 Cutler-Hammer QS4500TE0001 ATHI/ATVI QUICK START INSTRUCTIONS WARNING THIS INSTRUCTION IS NOT A COMPLETE SOURCE OF INFORMATION ON THE TRANSFER EQUIP- MENT. INSTALLATION SHOULD NOT BE STARTED UNTIL THE ENTIRE INSTRUCTION BOOK HAS BEEN REVIEWED AND UNDERSTOOD. FAILURE TO FOLLOW INSTRUCTIONS CAN RESULT IN DEATH, SEVERE PERSONAL INJURY, OR PROPERTY DAMAGE.
  • Page 2 QS4500TE0001 Page 2 Step 2: Install power cables. Cables shall be sized and N2, N3), [3] Emergency and Generator Supply (E1, E2, installed per National Electrical Code, refer to NFPA70. E3). For 4 pole transfer switches, connect load cables The cable must be sized within the specified cable size (T4), normal or utility supply (N4), and emergency or range on the side of the cable connectors.
  • Page 3 QS4500TE0001 Page 3 Tighten Cables Into Terminals See Detail Detail Typical Figure 3 Vertical Power Panel Figure 4 Horizontal Power Panel Step 3: Turn generator OFF at the Generator Control Terminals 51, and 52 (Red) (Figure 5). This contact is Panel.
  • Page 4 QS4500TE0001 Page 4 Step 5: Apply Utility (Normal) Power. If the switch is check for proper system voltage on the normal and load properly applied for the system voltage ordered, the dis- terminals. Check all phases on a three-phase switch. play should work and the Normal Source (Source 1) Voltage measurements should be taken phase to phase Available LED should light (Figure 6).
  • Page 5 QS4500TE0001 Page 5 Step 6: To view setpoints, press the <Display Select> <Step> pushbutton to step through the set points pushbutton until the Set Points LED lights. Use the (Figure 6 and Table 1). Table 1 Setpoint Possibilities Setpoint Setpoint Units Description Range Factory Default...
  • Page 6 QS4500TE0001 Page 6 Step 7: To change or add a setpoint, place the <Run - Program> switch on the rear of the IQ Transfer Logic unit in the Program position (Figure 7). The red LED next to Program on the front display will flash (Figure 6). Figure 7 IQ Transfer Logic (Rear View) Press the <Display Select>...
  • Page 7 QS4500TE0001 Page 7 Step 8: Manually start the engine generator at the gen- Step 9: Initiate a Load Test from the front panel of the erator controller (Figure 8). With the generator running, IQ Transfer (Figure 9). This may be done by making the check that the Emergency Source (Source 2) Available TMODE setpoint 1 and pressing the <Engine Test>...
  • Page 8: Off Position

    QS4500TE0001 Page 8 Step 10: ATHI/ATVI Power Failure Test - Initiate a Load This can be found in one of two places. The first Test by simulating an actual power failure. would be located directly beside the normal breaker. The second would be located on the transformer (1) This should be done by opening the upstream panel/customer connection panel.