Chapter 2 — Site Requirements
Fire Protection To comply with the OSHA Directive for Fixed
Extinguishing Systems (General, 1910.160), the library has a punch-out in
the cover for each frame and a corresponding cut-out in the top of each
frame for the purpose of attaching a hose or nozzle from your site's fixed
extinguishing system.
Fire extinguishing system punch-out,
main frame (top cover)
Fire extinguishing system cut-out,
(top cover removed)
Figure 11 Location of the fire extinguishing system access opening in top of library.
Shock and Vibration The library will operate normally after experiencing
shock loads as specified in the following table. The operating shock levels
indicate how much shock the library can withstand while the enclosed
drives are reading and writing data. The non-operating and storage shock
levels indicate how much shock the library can withstand when it is not
operating. After experiencing this amount of shock, the library will operate
normally.
Specification
Operating
Shock
2 g pk ½ sine wave for 10 msec
(3 axes, 2 shocks per axis, minimum)
Vibration
5 Hz – 500 Hz – 5 Hz
(Swept Sine)
5 – 22 Hz, 0.01-inch DA displacement
22 – 500 Hz, 0.25G pk @ ½ octave
(minimum three axes)
Vibration
0.5 Grms, 0 – 3000 Hz (single axis)
(Random)
a. Specifications are for the library in its original packaging.
February 2019
Storing and Shipping
(Non-Operating Environment)
2 g pk ½ sine wave for 10 msec
(3 axes, 2 shocks per axis, minimum)
5 Hz – 500 Hz – 5 Hz
5 – 31 Hz, 0.02-inch DA displacement
31 – 500 Hz, 1G pk @ ½ octave
(minimum three axes)
1 – 200 Hz @ 1.156 Grms.
Bottom face only for 60 minutes.
Site Preparation Guide—Spectra TFinity Library
Environmental Requirements
a
36

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TFinity and is the answer not in the manual?

Questions and answers

Table of Contents