Commissioning; Electrical And Piping; Flow Rate Adjustment - Deckma Hamburg OMD-2008 Instruction Manual

15ppm bilge alarm
Hide thumbs Also See for OMD-2008:
Table of Contents

Advertisement

10 Commissioning

See Section 2 for important notes.
On completion of the installation, wiring, and piping carry out the following
checks:

10.1 Electrical and Piping

a) Check that the power supply is connected to terminals 1 + 2 of the
terminal block.
b) Check that the wiring of the automatic stopping device (back-to-bilge
valve) and to the alarm system is according the IMO Requirements.
c) Check that the grounding (PE) connections have been made according to
the relevant regulations.
d) Check all piping connections for leaks and rectify as appropriate

10.2 Flow rate adjustment

a) Run oil free water through the instrument to purge the system. Measure
the amount of water flowing through the instrument per Minute. Flow rate
for both sample stream and clean water stream should be approx. 2 Liters
per Minute. On OMD-2008 FC instruments the flow rate can be read from
the display.
b) On OMD-2008 EV-FC instruments adjust the flow rate through the unit by
LOW FLOW
O-Ring 4.5x2 inside
using the small O-Rings in the cell cap.
Issue: 25.09.2015 preliminaryInstruction Manual OMD-2008 (All Versions)
DECKMA HAMBURG GmbH
MEDIUM FLOW
O-Ring 8.5x2 outside
HIGH FLOW
Main O-Ring 11.5x3 always present
Page 21 of 28